…From Controversy to Cooperation–what IWPC has been doing to save our regional water source

Potter Valley Project/New Eel Russian Facility
Update 8.20.2026
IWPC Press Release:  Work Underway to Advance Continued Diversion through the PVP.

Engineering work and collaboration on potential storage strategies show progress for protecting long-term water supply reliability

PR 3 – Geotechnical work on NERF 8.19.26

 

 

Update 7.9.2026
NERF Modeling Analysis Presentation

NERF Modeling Analysis Presentation_IWPC 7.9.2026

Sonoma Water has been modeling how transfers from the Eel River to the Russian River will be different than historical diversions as a result of the decommissioning of the Potter Valley Project and the construction of the New Eel-Russian Facility (NERF).

Under the NERF rules, there is water for diversion in all year types, even drought years such as 2020 and 2021, and water would have been diverted in water years 2025 and 2026.

In general, the average annual water available to be transferred through NERF under the Water Diversion Agreement each year is similar to transfers under the 2004 FERC License Amendment, but we need more Russian River storage to maximize those transfers because of change in seasonality of the transfers.

The Eel-Russian Project Authority continues to lead the effort to design, permit, and construct NERF so that water can continue to be diverted. Design and permitting are currently 100% funded.

 

 

 

Update 5.22.2026
FERC Scoping Document

FERC Scoping document 1 link2026 May 22 FERC Scoping Document 1

On Friday, May 22nd, the Federal Energy Regulatory Commission (FERC) released a Scoping Document for PG&E’s surrender and decommissioning of the Potter Valley Hydroelectric Project (PVP). In its Scoping Document, FERC stated that the Commission is reviewing PG&E’s application to surrender and decommission the PVP along with its joint proposal “to construct a New Eel-Russian Facility (NERF) for the purpose of water diversion through some of the project’s existing infrastructure” into the Russian River.

FERC will hold two in-person scoping meetings to receive comments on the scope of the NEPA document:

Evening Scoping Meeting, DATE: Tuesday, June 23, 2026

Time: 6:30 p.m.-8:30 p.m. Pacific Time (PT)

Ukiah Valley Conference Center, Chenin Blanc Room,  200 South School Street, Ukiah, CA 95482

Daytime Scoping Meeting   DATE: Wednesday, June 24, 2026

Time: 10:00 a.m.-12:00 p.m (PT)

Ukiah Valley Conference Center, Chenin Blanc Room, 200 South School Street, Ukiah, CA 95482

IWPC press release on scoping documentFERC Advances Review of Potter Valley Project Surrender and New Eel-Russian Facility 5.25.26

 

Original May 10, 2018, letter from PG&E stating that the auction for it’s PVP facilities would open in the Fall.

May 10, 2018
Eel-Russian River Commission
501 Low Gap Road, Suite 1010
Ukiah, CA 95482

Dear Eel-Russian River Commissioners:
During my February 23, 2018 presentation to the Eel-Russian River Commission, I informed you that
Pacific Gas and Electric Company (PG&E) was evaluating several options for the Potter Valley
Hydroelectric Project. I’m writing to let you know that after very careful consideration, PG&E has
decided to put the project up for auction this fall.
This decision to begin the auction process ultimately reflects that continuing to operate the facility is not
in the long-term best interests of PG&E’s electric customers. However, PG&E fully realizes that the
project has key environmental attributes and provides important regional benefits including recreation
opportunities and a significant contribution to the Russian River water supply.
With this in mind, as we prepare for the auction PG&E is open to exploring with local, county and/or
state governmental entities that have an interest in the continued operation of the project the possibility
of transferring it to a local or regional entity as an alternative to the auction. PG&E will assess the
progress of such transfer negotiations as they proceed, and based on meaningful progress, will either
continue direct negotiations or proceed with the auction.
Participation in the auction will be open to any qualified entity. Qualifications will include being able to
meet the Federal Energy Regulatory Commission’s (FERC) requirements for a hydroelectric project
licensee. We anticipate interest in acquiring the project by electric power interests, water supply
interests, potential combinations of these two groups and possibly by others. Transfer of the project will
require approval of both the FERC and the California Public Utilities Commission. The entire process
could take one-and-a-half to two years to complete.
PG&E plans to continue the ongoing FERC relicensing proceeding throughout the auction process with
the expectation that the new project owner will “step into PG&E’s shoes” relative to the relicensing once
regulatory approval of project transfer has been obtained.
Due to its relatively small electric generation capacity, divesting the Potter Valley Project will not
impact PG&E’s delivery of safe, clean, affordable and reliable electricity to our customers. The
divesture is expected to have a negligible impact on PG&E’s overall portfolio of renewable power.
Throughout the divestiture process, PG&E will continue to operate the Potter Valley Project as a
hydroelectric facility in full compliance with our FERC license and all applicable environmental laws
and regulations.
Best regards,
David Moller
Director, Power Generation

 

Update 11/17/2023
 PG&E has released its Initial Draft Surrender Application

PG&E has released its Initial Draft Surrender Application and Conceptual Decommissioning Plan for the Potter Valley Project and it is available for review and comment.  The document can be downloaded from the “Documents” tab at PG&E’s Potter Valley Surrender Proceeding website. When prompted for a password, enter “PV_Surrender”.  Instructions for providing comments on the document to PG&E are on page number 1-3.   You can obtain access to the application by reaching out to the PG&E Project Manager at  T1GF@pge.com.  The public comment period will be open until December 22, 2023. Formal comments must be submitted in writing via email to PVSurrender@pge.com or by mail to:

Tony Gigliotti
Senior Licensing Project Manager
Power Generation
12840 Bill Clark Way
Auburn, CA 95602

 PG&E will address comments as appropriate before distribution of the Final Draft Surrender Application in June 2024.  The initial draft includes PG&E’s conceptual decommissioning plan and a third-party proposal for modifications of the former Cape Horn Dam site and Van Arsdale Diversion, as necessary, to construct a New Eel-Russian Facility.  PG&E has not accepted the proposal at this time, but is including it as an option for Cape Horn Dam.  Proponents of the proposal include California Department of Fish and Wildlife (CDFW) California Trout, Humboldt County, Mendocino County Inland Water and Power Commission, the Round Valley Indian Tribes, Sonoma County Water Agency, and Trout Unlimited.  A copy of the Proponent’s Proposal is available at: https://www.sonomawater.org/pvp

PVP PGE Proposal  PVP PGE Proposal (2023-08-03)(final)

 

Update 10/17/2023
 New Trans Basin Diversion Proposal

Sonoma County Water Agency, Mendocino County Inland Water and Power Commission and the Round Valley Indian Tribes submitted a proposal for Cape Horn Dam and Van Arsdale Diversion to PG&E.  PG&E would include the proposal in the final license surrender application under certain conditions as outlined in the attached Proposal for Pacific Gas & Electric Company Draft License Surrender Application, Potter Valley Project.  This proposal may be revised, based on comments received.

PVP-Proposal-2023-08-03

On October 3, 2023, PG&E released the following statement on Sonoma/Mendocino/Round Valley Indian Tribes Proposal for Potter Valley Project’s Draft Surrender Application and Decommissioning Plan:

 PG&E has made a non-binding acceptance in concept of the Sonoma County Water Agency, Mendocino County Inland Water and Power Commission and the Round Valley Indian Tribes proposal and agrees to include it in our November 15th 2023 initial draft Surrender Application and Decommissioning Plan (SA). The acceptance of this proposal is non-binding and allows for continued discussion and public
Comment.  The initial Draft SA will be available for public review in November 2023 and will also include PG&E’s proposal to remove Cape Horn Dam.

  • This proposal states that it has co-equal objectives of fish migration and water diversions.
  • PG&E will include both the third-party proposal as well as our decommissioning plan in our initial Draft Surrender Application and Decommissioning Plan.

 

Update 8/7/2023
Proposal to preserve Potter Valley Diversion and Fish Passage
Proposal to Preserve Potter Valley Diversion and Fish Passage    https://www.sonomawater.org/

A Regional Partnership to secure water for the Russian River and to improve Eel River fisheries

The Mendocino County Inland Power and Water Commission (MCIWPC), Round Valley Indian Tribes (RVIT), and the Sonoma County Water Agency (Sonoma Water), collectively the proponents, have submitted a proposal Pacific Gas and Electric Company (PG&E) to advance a regional solution for preserving flows in the Russian River and improving Eel River fisheries.

Why is this needed?

In 2021, due to equipment failure at the powerplant, PG&E stopped generating power at the Potter Valley Project.  PG&E decided not to repair the powerplant.  It is preparing a license surrender application, to be filed with the Federal Energy Regulatory Commission (FERC). The deadline for application is January 2025.

PG&E has said that its application would propose to remove Scott and Cape Horn Dams and end any operations, including water diversions to the Russian River, unless it received a complete and credible proposal in July 2023.

The proponents submitted a proposal to PG&E to preserve water diversions into the Russian River watershed through the Potter Valley Project. The proposal is also important to assure that removal or modification of facilities allow for upstream and downstream fish migration at Cape Horn Dam, consistent with goals for a sustainable and harvestable Eel River fishery.

Ongoing water diversions into the Russian River through the Potter Valley Project are critical to the health of the watershed, to ongoing water supply, and to Russian River fisheries. Without the Potter Valley Diversion, Lake Mendocino would have shortages eight of every 10 years and would go dry two of every 10 years.

What does the proposal do?

The proposal includes creation of a regional entity to serve as a legal organization in discussing a New Eel-Russian Facility with PG&E.

The proposal seeks PG&E to include in its final license surrender application a request that the Federal Energy Regulatory Commission issue a nonpower license to the regional entity, which would preserve components of the modified Potter Valley Project diversion facilities and authorize the construction of the Eel-Russian facility.

The immediate role of this regional entity and the proposal is to preserve water diversions into the Russian River through the Potter Valley Project site while providing upstream and downstream fish migration to support larger efforts aimed at achieving naturally reproducing, self-sustaining and harvestable native anadromous fish populations.

The proposal has been shaped by insights provided through the Russian River Water Forum. Through the Forum, stakeholders and the public will have an opportunity to assist in the development of the details in the proposal.

For information about the proponents and the Russian River Water Forum, go to:

Articles on Proposal:

New Trans Basin Diversion Proposal

Sonoma County Water Agency, Mendocino County Inland Water and Power Commission and the Round Valley Indian Tribes submitted a proposal for Cape Horn Dam and Van Arsdale Diversion to PG&E.  PG&E would include the proposal in the final license surrender application under certain conditions as outlined in the attached Proposal for Pacific Gas & Electric Company Draft License Surrender Application, Potter Valley Project.  This proposal may be revised, based on comments received.

PVP-Proposal-2023-08-03

 

 

Update 7/14/2023
PG&E Flow variance request

Flow Variance
On May 22, 2023, PG&E filed a flow variance request with FERC for 2023. The flow changes that are requested are similar to last year, with the East Fork Russian River releases being reduced from the current 75 CFS to a release between 5-25 CFS based on PG&E and agency determinations of daily temperature evaluation of water released from Lake Pillsbury. FERC has opened up the variance request for public comments until August 4th.  It is anticipated that the variance will not go into effect until sometime in August.

The variance request can be seen HERE.

 

Update 6/2/2023
PG&E’s license surrender timelines

PG&E reported that, now that they have been directed by FERC to surrender and decommission the Project, they intend to remove all of the Project infrastructure including both Scott Dam at Lake Pillsbury and Cape Horn Dam at Van Arsdale reservoir.  PG&E will, however, review any plans that a qualified owner might submit in order to acquire part of the existing Project infrastructure.  PG&E wishes to receive notice of such a proposal as soon as possible.

Tony Gigliotti, PG&E’s Senior Project License Surrender Manager, laid out the timeline for the license surrender plan. There will be an initial draft surrender plan for public review released November 2023. A final draft surrender plan will be filed with FERC, and also available for public review, in May 2024. The final license surrender plan will be filed with FERC in January 2025.

 

Update 5/20/2023
Cape Horn Dam

As part of the RRWF’s DWR grant, one of the objectives was to assess the PVP facilities for possible acquisition.  One of the issues is that the current diversion facilities will require modification to improve fish passage.   The existing fish ladder is inadequate, so three alternatives are being considered. These include modifying Cape Horn Dam and installing a state of the art fish ladder.  The second alternative includes designing a gradual roughened channel allowing fish passage while maintaining the elevation needed for the diversion. The third concept is a facility that would pump water from an infiltration gallery downstream of the existing dam back up to the diversion tunnel. The DWR grant funding will result in a 20-30% design for these three alternatives.  Sonoma Water is applying for a grant from the Bureau of Reclamation (BOR) to determine the most feasible of the three alternatives and take that alternative to a 60% design.  IWPC is sending a letter of support for the BOR grant.

 

Update 4/27/2023
Scott Dam

PG&E held a town hall meeting on April 27 to talk about changes in operations they have made at Lake Pillsbury’s Scott Dam.  After a Safety Study that included a seismic analysis, they concluded that the 100 year old dam had an increase in seismic risk due to the Bartlett Springs fault that runs directly under Lake Pillsbury.  PG&E is opening the gates at the dam to reduce the lake level by ten feet which will reduce the pressure and risk of dam failure.

Lake Pillsbury has provided a reliable source of water to the Eel and Russian Rivers during the summer months when natural flows can be extremely low. On average, per annum, the Project diverts 1.8% of the flow in the Eel River through a diversion into the Russian River. However, maintenance of the aging dam is one of the reasons that the Potter Valley hydroplant is running at an economic loss for PG&E.   The costs of finding a solution for fish passage and building a suitable alternative plus correcting the identified seismic issues, make maintaining this dam even more expensive.

PG&E also reported that, now that they have been directed by FERC to surrender and decommission the Project, they intend to remove all of the Project infrastructure including both Scott Dam at Lake Pillsbury and Cape Horn Dam at Van Arsdale reservoir. PG&E will, however, review any plans that a qualified owner might submit in order to acquire part of the existing Project infrastructure. PG&E wishes to receive notice of such a proposal as soon as possible.

Tony Gigliotti, PG&E’s Senior Project License Surrender Manager, laid out the timeline for the license surrender plan. There will be an initial draft surrender plan for public review released November 2023. A final draft surrender plan will be filed with FERC, and also available for public review, in May 2024. The final license surrender plan will be filed with FERC in January 2025.

Sonoma Water is applying for a grant from the Bureau of Reclamation to bring one of the three Eel River diversion plan alternatives, that will allow volitional fish migration passage and continued diversions into the Russian River watershed (currently being studied with grant funding from DWR), to a 60% design level.

 

Current Infrastructure Challenges

Since the transformer unit at the PVP is not being repaired, PG&E is not able to run water through the powerhouse to make power and has only been bypassing the minimum amount of water as required by their license for the East Fork Russian River and the Potter Valley Irrigation District.

  • The reduced diversion has impacted, and will continue to impact, the water storage levels in Lake Mendocino.
  • 4/2023: PG&E has delayed the decision regarding the transformer replacement at the PVP until April 2023.  At that time they announced that there would be no replacement of the transformer.  See letter from PG&E:  PG&E Transformer Replacement Update 12.22
  • 10/2022: PG&E revealed in late October 2021 that an electric transformer necessary for the operation of the powerhouse had degraded to a point that it was at risk of failing. Preliminary estimates indicate an expected timeline of 18 to 24 months to design, manufacturer, and install, with a cost in the $5 to $10 million range.  And in February 2022, it was announced that PG&E has, “concluded it is beneficial to PG&E’s electric generation customers to proceed with the work necessary to return the powerhouse to full operational status.” No specific timelines for the repairs were presented, but overall, this is positive news.

 

Licensing Challenges
  • On April 21, 2022, FERC provided a notice stating that PG&E has been authorized to continue to operate the Project under a year-to-year license or until the issuance of a new license for the project or other disposition under the Federal Power Act, whichever comes first.
  • On May 11, 2022, FERC submitted a response to PG&E requesting a license surrender plan to be submitted within 60 days.
  • The timeline for the year-to-year operation is currently unknown as are the details of the license surrender plan. The Mendocino County Inland Water & Power Commission will continue to engage with PG&E and other stakeholders as the process moves forward.
Eel Russian Project Authority (ERPA)

July 21, 2025 ERPA Board meeting

 

Update 3/12/2024
ERPA meeting

The Eel Russian Project Authority (ERPA) will be holding their next meeting in Ukiah on March 19 from 3-5 pm.  They will be meeting in the Mendocino County Supervisors chambers and be on zoom as a webinar.

Here is the link to see the details and agenda:  https://www.eelrussianauthority.org/events

 

Update 2/14/2024
PG&E to transfer certain PVP assets and the water rights to the Eel Russian Project Authority (ERPA)

PG&E recently made an announcement regarding the PVP decommissioning, that shocked some people as they assumed it was the end for the new Eel/Russian diversion and fisheries plan.  But that is totally incorrect…everything is moving forward, just in a slightly different way.

As we had reported previously, Mendocino County Inland Water & Power Commission (IWPC) has been working on a way for PG&E to transfer certain PVP assets and the water rights to the Eel Russian Project Authority (ERPA).  A Joint proposal was sent from IWPC, Sonoma Water Agency, Round Valley Tribes, CA Dept. of Fish and Wildlife, Trout Unlimited, Cal Trout and Humboldt County to PG&E.  Basically, it stated that we would take over certain physical assets from PG&E and find a way to divert water in such a way as to allow water to flow to the Russian River and yet maintain flows and improve fisheries in the Eel River.

To do that, we formed the Eel Russian Project Authority (ERPA) consisting of Sonoma County Water, Sonoma County, and IWPC, with the Round Valley Indian Tribe also having a vote on the Board.  ERPA met for the first time on January 31, 2024.  You can watch the video of the meeting at this link: https://www.eelrussianauthority.org/events.

ERPA would request a non-power license from FERC as part of the regulatory process. Once FERC and state permitting were complete, we would work in concert with PG&E as they removed their facilities and at the same time, we would be building our facilities.  PG&E accepted the proposal for further evaluation in November 2023.

However, later in February, PG&E told the group that there were aspects of our proposal that did not align with their timelines for dam removal.  The main concern was the time it might take to obtain a FERC non-power license and therefore they were not going to include our ‘complete’ proposal in their decommissioning plan to FERC.  However, they were still willing to include parts of it and work with us in many ways that will support the efforts of ERPA.

So instead, PG&E will work independently on FERC permitting, but we will work in parallel with PG&E to accomplish the various state permitting requirements.  Once all permitting is complete, as PG&E removes their facilities, we will be building our facilities at the same time.

So, long story short, this is just another stage in our continued and ‘parallel’ progress forward…it’s just a little different path but the work will definitely continue, and the goals are the same.   We are now in a period where we are trying to evaluate the best permitting strategy to make sure there is no daylight between PG&E’s removal of the dam and our construction of the new facility and diversion.  There are a lot of things we can work with PG&E on, so we will continue to meet and work with them.

 

Update 12/8/2023
Approval of JPA with IWPC to form Eel-Russian Project Authority

The Sonoma County Board of Supervisors, who also serve as the Board of Directors for the Sonoma County Water Agency, voted today to approve a Joint Exercise of Powers Agreement with Mendocino County Inland Water and Power Commission to form the Eel-Russian Project Authority.

The new entity will have the power to negotiate with the Pacific Gas and Electric Company (PG&E) as the utility moves ahead with plans to surrender operations of the Potter Valley Hydroelectric Project and to decommission the Scott and Cape Horn dams on the Eel River. The new authority will also have the legal capacity to own, construct and operate a new water diversion facility near the Cape Horn dam.

“This is another important step in the process to find a truly regional solution to the challenges facing the Eel and Russian River watersheds,” said Sonoma County Supervisor and Sonoma Water Director David Rabbitt. “We’re grateful to all of the partners who are working diligently to achieve our co-equal goals of continued diversions into the Russian River and improving fisheries in the Eel River.”

The Potter Valley Project, currently owned and operated by PG&E, has been diverting water from the Eel River into the Russian River watershed for more than a century, playing a critical role in supplying water for agriculture, homes, and instream flows to benefit aquatic ecosystems and threatened salmonids in Mendocino and Sonoma counties.

The Potter Valley Project is licensed by the Federal Energy Regulatory Commission. In 2019, PG&E announced that it would not proceed with relicensing the project and would instead enter into a license surrender and decommissioning process. PG&E stated that its application would propose to remove Scott and Cape Horn dams and end any operations, including water diversions to the Russian River, unless it received a complete and credible proposal by July 2023.

To meet this deadline, in July, the Mendocino County Inland Water and Power Commission, the Round Valley Indian Tribes and Sonoma Water submitted a proposal to PG&E to preserve water diversions into the Russian River, while also prioritizing upstream and downstream fish migration in the Eel River. The California Department of Fish and Wildlife, County of Humboldt, California Trout and Trout Unlimited subsequently signed on to a revised proposal in November.

PG&E released an initial draft surrender application on Nov. 17, 2023 which includes several of the measures proposed by the coalition. PG&E is set to release a final draft surrender application in June 2024. The final application is expected to be submitted by Jan. 29, 2025.

The New Eel-Russian Facility proposal submitted to PG&E also called for the creation of a regional entity, which today’s board action will move forward, with the capacity to develop a yet-to-be designed facility that would allow for ongoing water diversions through the Potter Valley Project’s tunnel between the Eel River and Russian River, while providing for fish migration to support naturally reproducing and self-sustaining native fish populations.

The Eel-Russian Project Authority’s five-member board of directors will initially consist of two representatives from the Mendocino County Inland Water and Power Commission, one from Sonoma Water, one from the County of Sonoma and one from the Round Valley Indian Tribes.

For more information, visit https://sonomawater.org/pvp.

Dec. 5, 2023   Press release link:

Sonoma Water, Sonoma County approves formation of Eel-Russian Project Authority

 

Update 8/22/2023
Proposal to preserve Potter Valley diversion and fish passage
Proposal to Preserve Potter Valley Diversion and Fish Passage    https://www.sonomawater.org/
From Press Democrat article 8/8/2023 referenced below:

       Sonoma Water officials say the new proposal would still allow for removal of Scott and Cape Horn dams, leaving only the infrastructure necessary to funnel river water through the mile-long tunnel that leads to the East Fork Russian River.Additional infrastructure would be added to improve fish passage and aid restoration of salmon and steelhead trout populations in the Eel River, as sought by tribes and conservation groups, while still channeling water into the diversion tunnel, Sonoma Water officials said.

“Our goals are to restore the Eel River watershed from its degraded condition and to restore our salmon fishery to sustainable and harvestable populations,” Round Valley Indian Tribes Tribal Council President Bill Whipple said in a news release. “We join this proposal because it is one pathway to achieving these goals.”

The diversion of Eel River water through what’s being called the New Eel-Russian Facility also would occur only during wet months, when flows are sufficiently high to support salmon and steelhead trout in the Eel while still contributing to Russian River water supplies on which thousands of consumers depend.

“We are going to dramatically reduce the window in which water can be diverted off the Eel River to times it’s very available and won’t do harm,” Sonoma Water General Manager Grant Davis said. “We really want to see both river basins come out better as a result of this solution.”

Water supply and storage
Update 8.9.2026

New Modeling Confirms Water Will Be Available Through Future New Eel-Russian Diversion Facility

Analysis reinforces the region’s path forward with new diversion infrastructure, secured water rights, and expanded storage to protect long term water reliability following PG&E decommissioning of Potter Valley Project

(Ukiah, CA — xx, 2026)  New water supply modeling confirms that water would be available for diversion from the Eel River into the Russian River watershed through the proposed New Eel-Russian Facility, including during drought years.

The analysis, completed by Sonoma Water, evaluated how water transfers would have occurred in past years, under the diversion rules that have now been established in the 2025 multi-party Water Diversion Agreement. It modeled potential transfers through the NERF over the past 13 years and found that water would have been available for diversion in every year and across all water-year types.

“The modeling confirms that the New Eel-Russian Facility can work, and that water will truly be available for diversion, every year, including during drought years,” said Dave Koball, Alternate Commissioner for Mendocino County IWPC. “It also reinforces why diversion and storage must be pursued together. Additional storage will allow us to capture more water when it is available and preserve it for the farms, businesses and communities that need it later in the year.”

The modeling shows that there would have been possible water transfers through the NERF that ranged from approximately 18,000 acre-feet during the severe 2021 drought, to approximately 86,000 acre-feet in the wet year of 2017. For the most recent 21 months analyzed (Oct 2024 – June 2026), the modeling shows that stored transfers through the NERF would have totaled approximately 52,000 acre-feet, compared to the approximately 56,000 acre-feet in stored transfers that were actually observed under the existing system. These values are preliminary and will be updated as new information becomes available.

In general, the average annual volume available for transfer through the NERF under the Water Diversion Agreement will be similar to transfers that have occurred historically under the Potter Valley Project’s current license. The major difference is the timing of water availability for transfers. More water would be available during wet winter months, when existing storage options may already be full. That reinforces the need to pursue additional, expanded storage options.

The analysis found that during non-drought years, an average of approximately 40,000 acre-feet of additional water could be put to use each year if more storage were available in the Russian River watershed.

These findings reinforce the efforts of IWPC and regional partners to respond to PG&E’s decommissioning plans through a coordinated plan to:

  • Uphold the multi-party Water Diversion Agreement, which provides the legal framework for continued diversions after PG&E’s exit.
  • Support the Eel-Russian Project Authority’s work to design, permit and construct the NERF to move water from the Eel River into the Russian River watershed.
  • Expand regional storage so water available during wetter months can be captured for use during the dry season and drought years.

“We have the essential elements of a workable solution: an agreement protecting continued diversions, a locally governed agency advancing the new facility, and identified opportunities to expand storage,” said Mari Rodin, IWPC Commissioner and City of Ukiah Councilmember. “The modeling confirms that the region is moving in the right direction. Our focus now is on putting those pieces into place.”

The complete modeling presentation is available here.  Full video and audio here:  https://www.youtube.com/watch?v=okXsC29dZ3I

Jan/Feb 2026
Presentations on Potential Water Supply Storage Options

Jan 8 2026 IWPC Storage options

Storage Options Feb 12 2026

 

Update 7/2025
Potter Valley Water Supply Reliability Study

When PG&E announced in 2019 their intention to decommission and remove Scott and Cape Horn dams, it meant the end of water diversion operations to the Russian River and to 600,000 people, agriculture and fish migration.  In response, the Mendocino County Inland Water & Power Commission, the Round Valley Indian Tribes and Sonoma County Water Agency formed a new entity, the Eel-Russian Project Authority to preserve water diversions into the Russian River, while also prioritizing upstream and downstream fish migration in the Eel River.  While the Potter Valley Project historically maintained a year-round water diversion, the proposed facility would use run-of-river operations which would essentially divert water during the wet season.

This change in operations would dramatically impact Potter Valley as it is above Lake Mendocino releases.  Sonoma Water acquired funding from the CA Department of Water Resources to support water resource investigations in the Potter Valley.  This Potter Valley Water Supply Reliability Study was developed to evaluate potential water management strategies in the Potter Valley Groundwater Basin.   Click the link below to see the final report.

PV Jacobs Water SupplyReliability Study 2025

 

Update 1/2025
4-minute video on Changes Coming to Your Water Supply  

Find out what has happened and where we are going from here in this informative 4-minute video.  Regional cooperation is essential to protect our collective future and to provide a resilient, responsible and enduring water supply.  Video link: Changes Coming to Your Water Supply

 

Update 11.14.2024
Potter Valley Water Supply Reliability Study Presentation

This video covers the presentation on the Potter Valley water resources investigation that was provided at the November 14, 2024 Town Hall meeting in Potter Valley.

Here is the link to see the video: Potter Valley Water Supply Reliability Study Town Hall Presentation – November 14, 2024

Update 8/22/2023
Proposal to preserve Potter Valley Diversion and Fish Passage
From Press Democrat article 8/8/2023 referenced below:

       Sonoma Water officials say the new proposal would still allow for removal of Scott and Cape Horn dams, leaving only the infrastructure necessary to funnel river water through the mile-long tunnel that leads to the East Fork Russian River.Additional infrastructure would be added to improve fish passage and aid restoration of salmon and steelhead trout populations in the Eel River, as sought by tribes and conservation groups, while still channeling water into the diversion tunnel, Sonoma Water officials said.

“Our goals are to restore the Eel River watershed from its degraded condition and to restore our salmon fishery to sustainable and harvestable populations,” Round Valley Indian Tribes Tribal Council President Bill Whipple said in a news release. “We join this proposal because it is one pathway to achieving these goals.”

The diversion of Eel River water through what’s being called the New Eel-Russian Facility also would occur only during wet months, when flows are sufficiently high to support salmon and steelhead trout in the Eel while still contributing to Russian River water supplies on which thousands of consumers depend.

“We are going to dramatically reduce the window in which water can be diverted off the Eel River to times it’s very available and won’t do harm,” Sonoma Water General Manager Grant Davis said. “We really want to see both river basins come out better as a result of this solution.”

 

Water Supply Challenges
  • Without PVP water transfers to the Russian River:
    • In 8 out of 10 years there will not be enough water supply in Lake Mendocino to meet all the needs of businesses, cities, residents, and wildlife that depend on the Russian
    • In 2 out of these 8 water-short years, there is predicted to be a 30,000-acre foot shortage of water in the Russian River, and Lake Mendocino is predicted to go dry
  • Water users that rely on Lake Mendocino for their water supply will be impacted to varying degrees depending on their location and water use.
  • Farther reaching economic and environmental impacts are also anticipated in Mendocino and Sonoma counties with the loss of PVP
Workshops
Nov. 24, 2025
Informational Workshop on the PVP and the future of our water

Video link: Mendocino County Inland Water and Power Comission Workshop – YouTube

Attendees received updates on planning efforts, future infrastructure needs, existing agreements, timelines related to PG&E’s decommissioning application and ongoing storage investigations from Potter Valley and south within the Russian River watershed.

 

May 29, 2025 All Boards Meeting

The following documents include the PowerPoint presentation and meeting recording from the All Boards meeting of the Mendocino County Inland Water and Power Commission (Commission) held on May 29th in Ukiah.  PG&E has made the decision to surrender their hydropower license and remove all of the infrastructure of the Potter Valley Project including Scott and Cape Horn Dams on the Eel River. The information included here will give you a comprehensive overview of what your local Commission, along with its regional partners, are doing to preserve the diversion from the Eel River. The steps taken over the last five years balance the needs of people, farms, fish, and the environment.

1. These are two handouts that summarizes the efforts of IWPC and our Regional partners:

 IWPC Securing Water for the Future 2 page handout 5-29-25

 IWPC Key Message Platform 5-29-25

 

2. These following two links contain a video and PowerPoint presentation made at the May 29th IWPC All Boards meeting that covers the history, current developments and future of our region’s water source:

https://ukiahca.portal.civicclerk.com/event/2298/media

2025 IWPC All Boards v.5 FINAL(4979861.2)

Documents & Press Releases
  • IWPC Press Release:
NERF Modeling Analysis Presentation

NERF Modeling Analysis Presentation_IWPC 7.9.2026

  • IWPC Press Release:  Work Underway to Advance Continued Diversion through the PVP

PR 3 – Geotechnical work on NERF 8.19.26

 

  • Securing Water for our Future Handout   

 2-page handout final 3.31.26

  • ERPA’s Document page

http://www.eelrussianauthority.org/reports

 

  • PG&E’s final surrender application with FERC 7.25.25

Final Surrender Application Filing with FERC

  • Water Diversion Agreement for the New Eel Russian Facility (NERF):

Water Diversion Agreement for New Eel Russian Facility 7.2025

  • Potter Valley Water Supply Reliability Study:

PV Jacobs Water Supply Reliability Study 2025